The project, with an investment of over 1.4 million euros, will be subject to public information to improve road safety and mobility on a road that handles an average of 15,000 vehicles per day. The new path will be 2.02 meters wide and will be constructed with earthy-toned pavement.
It will also include drainage works, repainting of road markings, vertical signage, and the installation of conduits for lighting and telecommunications. Benches will also be installed in various areas.
Once the public information period is concluded, the project will be definitively approved. The plan is to tender, award, and begin construction in the second half of 2027, with an execution period of 18 months. The works will be financed by Feder 21/27 funds.