UFD, Naturgy's electricity distributor, has completed the commissioning of the new underground medium-voltage line in the Sequeiro area, on the AC566 road. The intervention, which involved an investment of around 200,000 euros, aimed to modernize the area's electrical infrastructure and improve the quality and reliability of the supply.
The work allowed for the burial of the medium-voltage line, the removal of a total of 9 electrical poles, and the renewal of two transformation centers (CT). The new line has been energized and in service since yesterday, enabling the removal of the generator sets that were used to ensure the electricity supply during the works.
This action is part of UFD's plan to reinforce and modernize the electricity distribution network in Galicia, increasing its capacity, reliability, and resilience.